In this article, you can learn how to manage various calendars in the Scheduler function of Aidi.
The management of global calendars is done in the List mode view:
- Click on the 3 dots menu to the right of the Project Summary timeline (first line)
- Select Manage calendars
- By default, a "Weekday" calendar is applied for all old and new schedules
- If nothing is selected, the calendar will only allow working on days from Monday to Friday
- For projects requiring work on all 7 days of the week, select 7 days
- Click Save
This selection applies to the entire project schedule.
✏️ Note: These calendars, known as global calendars, cannot be modified by users, but can be applied to all tasks of a project individually. In general, it is the organization that manages the calendars in this list.