Goal: close a completed purchase order by bringing the committed amounts down to what was actually invoiced. The unused amount is credited back to the project's available financing and, where applicable, to the framework contract.
Example: a $10,000 purchase order is complete, but only $2,500 has been invoiced. When you close it, its amount drops to $2,500: the remaining $7,500 is no longer committed.
Prerequisites
- Be an administrator or have write access to purchase orders.
- The purchase order is Approved.
- None of the following purchase order documents is In preparation or In approval:
- Change order (CO);
- Payment request;
- Invoice.
- All expected invoices are entered and approved: the last approved invoice is used as the reference.
Change requests/directives still In preparation or In approval on this purchase order do not block closing: they are cancelled automatically. If they need to be kept, approve or process them before closing the purchase order.
Steps
- Open the purchase order.
- In the top bar, click Close (padlock icon).
- Read the confirmation message: “Each purchase order item will be adjusted to its invoiced amount. Are you sure you want to close this purchase order?”
- Confirm.
If linked items are still in preparation or in approval, the Unable to close the purchase order window lists them (type, reference and status). Approve, reject or cancel them, then try again.
Result
- The purchase order status changes to Closed.
- Each line is brought down to the amount invoiced up to the last approved invoice:
- the unit price does not change;
- the quantity is recalculated;
- a line that was never invoiced drops to $0;
- parent lines add up their child lines.
- The purchase order amount becomes the sum of the adjusted lines. The revised total decreases by the same amount.
- A Variance at closing line appears in the purchase order summary. It shows the amount released (revised amount − amount at closing).
- The committed amount in the cost summary decreases by the same variance: the released amount becomes available again in the budget and financing.
- If the purchase order is linked to a framework contract, the variance becomes available again on that framework contract.
- Change requests/directives still in preparation or in approval are cancelled.
- The purchase order history shows “Closed by … on …”.
What you can no longer do on a closed purchase order
- Create a payment request, an invoice or a contract modification. The message “Cannot create, the purchase order is closed.” is displayed.
- Create a payment request with SmartDoc. The document can be read, but SmartDoc indicates that the purchase order is closed and does not offer to create the request.
Reopen a closed purchase order
If it was closed too early, for example because an invoice is still coming in:
- Open the closed purchase order.
- Click Reopen (open padlock icon).
- Confirm: “Are you sure you want to reopen this purchase order?”
Result
- Each line gets back its original quantity and amount (from before closing).
- The revised total is restored and the status goes back to Approved.
- The history shows “Reopened by … on …”.
Change requests/directives cancelled at closing are not restored. If needed, put them back in preparation one by one.
Common issues
| Situation or message | Cause | What to do |
|---|---|---|
| The Close button is not shown. | The purchase order is not Approved, it is already closed, or you don't have write access to purchase orders. | Get the purchase order approved, or request access. |
| “The purchase order cannot be closed, the following documents are in preparation or in approval: …” | A CO, payment request or invoice is not completed. | Process each listed document, then close again. |
| The closed amount is lower than expected. | Amounts were declared in approved payment requests but not yet invoiced: only invoicing counts. | Reopen the purchase order, enter the missing invoice and get it approved, then close again. |
| The variance at closing is smaller than the remaining balance. | Approved contract modifications keep their amount: only the lines of the original purchase order are adjusted. | If needed, reduce unused modifications with a negative modification before closing. |
| “Cannot create, the purchase order is closed.” | You are trying to add a payment request, invoice or modification to a closed purchase order. | Reopen it if that document is needed. |
Comments