In the Monitoring / Cost summary section, you can view all the financial information for your project.
The Trend value is calculated as follows: Committed Amount + Amount to come
Committed amount = approved purchase orders + approved contractual changes
Amount to come = purchase orders yet to be committed + pending contractual changes + future risks + reserved budget (amount of budget items for which no expenditure has been committed).