Introduction
The changes in financing management are generally related to the following three pages:
- Project Financing
- Budgets
- Cost Summary
The function of associating financing revisions with budget versions was introduced in past updates. Approved budgets reflect the financing status at the time of approval. For example, when defining the budget, one can choose a financing source (either the original amount or a revised amount). The total financing amount for the component is reflected in the cost summary.
A new configuration has been added to the administrator's configuration panel to allow a choice to be made as to whether a new financing or new financing revision should be linked to all existing budgets or only to budgets In Preparation.
The intent is to provide a greater level of flexibility and traceability for managing the links between financing and budgets. The checked option provides greater traceability and history of links between budget versions and financing revisions, but restricted flexibility in adding, modifying and deleting revisions. Conversely, the unchecked option provides more flexibility and latitude for users, but reduced traceability.
Note: This selection applies to all projects in the structure.
Project Financing
Revisions can be made to project financing. Revisions change the amount of financing and are reflected in the Total revised amount field. The starting amount of the financing is now called the Initial amount.
In addition, from the Revisions section, it is possible to see the history of all revisions and their respective changes.
Creating a New Revision
Prerequisites:
-
-
- An existing project financing
-
- Write permissions on the project financing page
Steps:
- In the project financing, under the Revisions section, click on the Add Revision button.
- In the menu to create a revision, you can:
a. Define the revised amount (i.e. an amount that adds to the current total amount).
i. The total revised amount is set automatically after insertion.
b. Define the total revised amount (i.e. the actual financing amount)
i. The revised amount is defined automatically after the insertion.
c. Add a comment.
Note: If taxes are defined in your environment, it is possible to enter the amounts before or after taxes in the creation modal of the financing revision. The taxed amounts are updated by clicking on the creation modal after entering a Revised Amount or a Total Revised Amount.
Notes on the behaviour of revisions
- Only the last financing revision can be modified/deleted. Previous revisions are read-only. If the last revision is deleted, then the previous version becomes editable.
- The following rules apply to revisions based on increases & decreases:
- In the case of a negative revision (decrease in financing), the sum of a component's financing must remain greater than the sum of the amounts already obligated (approved purchase orders, approved billable contract changes, and active operations expenditures related to the budget).
- In the case of a positive revision (increase in financing), the increase must not exceed the Financing allowed associated with the Project financing.
Summary of Financing Management Logic and Revisions | ||
Actions | Financing Management | Financing Revisions Management |
Creation |
With financing functionality linked to budgets “In preparation only” activated:
Financing functionality linked to all budgets:
|
With financing functionality linked to budgets “In preparation only” activated:
Financing functionality linked to all budgets:
|
Modification |
With financing functionality linked to budgets “In preparation only” activated:
Financing functionality linked to all budgets:
|
With financing functionality linked to budgets “In preparation only” activated:
Financing functionality linked to all budgets:
|
Deletion |
With financing functionality linked to budgets “In preparation only” activated:
Financing functionality linked to all budgets:
|
With financing functionality linked to budgets “In preparation only” activated:
Financing functionality linked to all budgets:
|
Budget
It is now possible, from the budget, to:
- Select the initial amount, or a revision, for each financing in the budget
- Associate a financing revision to a budget item
- Freeze the history of the budget/financing revision associations as soon as they are launched for approval
Selecting a financing revision for a budget
Prerequisites:
- Project financing with at least 1 revision
- A budget
- Write access to the Budget page
Steps:
- In the budget, click on the arrow next to the Global financing amount.
- From the menu, you can select the desired financing revision.
By default, the amount selected in the previous budget version will be selected. This selection can be changed depending on the status of the budget and the configuration of the environment.
Notes:
- Only 1 financing revision can be selected per financing source for a budget
- When a new budget version is created, all financing and financing revisions related to the approved budget version are copied.
Type of user with rights to modify links between budgets and financing revisions | |||||
Budget Status | In preparation | Waiting approbation | Approved | Cancelled | Archived |
Financing linked to all budgets |
Administrator User with write permission for the budget |
Administrator User with write permission for the budget |
Administrator User with write permission for the budget |
None | None |
Financing linked to budgets In preparation only |
Administrator User with write permission for the budget |
Administrator | Administrator | None | None |
Impact and consideration of financing or financing revision added by status of budget versions | |
In preparation |
|
Waiting approbation |
|
Approved |
|
Archived |
|
Archived or Cancelled |
|
Impact on Cost Summary
When a financing revision is linked to a budget and that budget is approved, the financing amount displayed in the Cost Summary list includes the sum of all financing revision amounts that are linked to the approved budget. If a financing revision is linked to an In preparation budget, the revision amount will not be included in the financing amount shown in the Cost Summary.